9483    Date Filed:  June 08, 2018
IN THE MATTER OF THE APPLICATION OF CITIZENS UB SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 9.9 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN THE TOWN OF UNION BRIDGE AND CARROLL COUNTY, MARYLAND.

9482    Date Filed:  May 31, 2018
IN THE MATTER OF THE APPLICATION OF CP CRANE LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AUTHORIZING THE MODIFICATION OF THE CHARLES P. CRANE GENERATING STATON IN BALTIMORE COUNTY, MARYLAND.

9477    Date Filed:  January 23, 2018
IN THE MATTER OF THE APPLICATION OF CHERRYWOOD SOLAR I, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 202 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN CAROLINE COUNTY, MARYLAND.

9471    Date Filed:  December 27, 2017
IN THE MATTER OF THE APPLICATION OF TRANSOURCE MARYLAND LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT TWO NEW 230 KV TRANSMISSION LINES ASSOCIATED WITH THE INDEPENDENCE ENERGY CONNECTION PROJECT IN PORTIONS OF HARFORD AND WASHINGTON COUNTIES, MARYLAND

9470    Date Filed:  December 22, 2017
IN THE MATTER OF THE APPLICATION OF THE POTOMAC EDISON COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO MODIFY THE RINGGOLD-CATOCTIN TRANSMISSION LINE N FREDERICK AND WASHINGTON COUNTIES, MARYLAND.

9469    Date Filed:  December 21, 2017
IN THE MATTER OF THE APPLICATION OF ENERGY VENTURES IPP, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 10 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN PRINCE GEORGE'S COUNTY, MARYLAND

9466    Date Filed:  November 09, 2017
IN THE MATTER OF THE APPLICATION OF TPE MARYLAND SOLAR LAND HOLDINGS, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 2.25 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN PRINCE GEORGE'S COUNTY, MARYLAND (PRINCE GEORGE'S COUNTY 18).

9465    Date Filed:  November 09, 2017
IN THE MATTER OF THE APPLICATION OF TPE MARYLAND SOLAR LAND HOLDINGS, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 2.425 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN PRINCE GEORGE'S COUNTY, MARYLAND (PRINCE GEORGE'S COUNTY 21).

9464    Date Filed:  September 26, 2017
IN THE MATTER OF THE APPLICATION OF MD SOLAR 1, LLC FOR THE CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 32.5 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN CHARLES COUNTY, MARYLAND

9463    Date Filed:  September 25, 2017
IN THE MATTER OF THE APPLICATION OF MD SOLAR 2, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 27.5 MW SOLAR PHOTOVOLTAIC GENERATION FACILITY IN CHARLES COUNTY, MARYLAND.

9457    Date Filed:  September 06, 2017
IN THE MATTER OF THE APPLICATION OF RICHFIELD SOLAR ENERGY LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 50 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN DORCHESTER COUNTY, MARYLAND.

9454    Date Filed:  June 14, 2017
IN THE MATTER OF THE APPLICATION OF BRICK KILN ROAD SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 5.4 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WICOMICO COUNTY, MARYLAND.

9451    Date Filed:  May 10, 2017
IN THE MATTER OF THE APPLICATION OF CHESAPEAKE SOLAR LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 9.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN CECIL COUNTY, MARYLAND.

9450    Date Filed:  April 25, 2017
IN THE MATTER OF THE APPLICATION OF CASPER SOLAR CENTER, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 36.70 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN QUEEN ANNE'S COUNTY, MARYLAND.

9446    Date Filed:  April 11, 2017
IN THE MATTER OF THE APPLICATION OF SOL PHOENIX SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 2.5 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN PRINCE GEORGE'S COUNTY, MARYLAND.

9439    Date Filed:  February 17, 2017
IN THE MATTER OF THE APPLICATION OF BIGGS FORD SOLAR CENTER, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 15.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN FREDERICK COUNTY, MARYLAND.

9438    Date Filed:  December 23, 2016
IN THE MATTER OF THE APPLICATION OF MORGNEC ROAD SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 57.04 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN KENT COUNTY, MARYLAND.

9437    Date Filed:  December 22, 2016
IN THE MATTER OF THE APPLICATION OF CPV MARYLAND, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AUTHORIZING THE MODIFICATION OF ITS ST. CHARLES GENERATING STATION.

9436    Date Filed:  December 21, 2016
IN THE MATTER OF THE APPLICATION OF JONES FARM LANE SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 56.70 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN QUEEN ANNE'S COUNTY, MARYLAND.

9434    Date Filed:  December 20, 2016
IN THE MATTER OF THE APPLICATION OF EGYPT ROAD SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 45.90 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN THE CITY OF CAMBRIDGE, MARYLAND.

9429    Date Filed:  October 07, 2016
IN THE MATTER OF THE APPLICATION OF LEGORE BRIDGE SOLAR CENTER, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 20.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN FREDERICK COUNTY, MARYLAND

9426    Date Filed:  September 19, 2016
IN THE MATTER OF THE APPLICATION OF MASON DIXON SOLAR CENTER, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 18.4 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WASHINGTON COUNTY, MARYLAND.

9413    Date Filed:  January 14, 2016
IN THE MATTER OF THE APPLICATION OF DAN'S MOUNTAIN WIND FORCE, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 59.5 MW WIND ENERGY GENERATING FACILITY IN ALLEGANY COUNTY, MARYLAND

9412    Date Filed:  December 21, 2015
IN THE MATTER OF THE APPLICATION OF TODD SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 20.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN DORCHESTER COUNTY, MARYLAND

9409    Date Filed:  December 01, 2015
IN THE MATTER OF THE APPLICATION OF GATEWAY SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 12 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WORCESTER COUNTY, MARYLAND

9408    Date Filed:  December 01, 2015
IN THE MATTER OF THE APPLICATION OF PERENNIAL SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT AN 8.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WASHINGTON COUNTY, MARYLAND

9407    Date Filed:  November 09, 2015
IN THE MATTER OF THE APPLICATION OF MASSEY SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 5.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN KENT COUNTY, MARYLAND

9405    Date Filed:  November 06, 2015
IN THE MATTER OF THE APPLICATION OF LONGVIEW SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 15.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WORCESTER COUNTY, MARYLAND (LS-SEABEACH SOLAR FARM)

9403    Date Filed:  October 30, 2015
IN THE MATTER OF THE APPLICATION OF LONGVIEW SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 20.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WORCESTER COUNTY, MARYLAND

9402    Date Filed:  October 29, 2015
IN THE MATTER OF THE APPLICATION OF BIG SPRING SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 3.5 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WASHINGTON COUNTY, MARYLAND

9400    Date Filed:  October 20, 2015
IN THE MATTER OF THE APPLICATION OF DAN'S MOUNTAIN SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 18.36 MW SOLAR PHOTVOLTAIC GENERATING FACILITY IN ALLEGANY COUNTY, MARYLAND

9399    Date Filed:  October 08, 2015
IN THE MATTER OF THE APPLICATION OF ONEENERGY BAKER POINT SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 9.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN FREDERICK COUNTY, MARYLAND

9395    Date Filed:  September 04, 2015
IN THE MATTER OF THE APPLICATION OF PINESBURG SOLAR LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT AN 8.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WASHINGTON COUNTY, MARYLAND

9392    Date Filed:  August 21, 2015
IN THE MATTER OF THE APPLICATION OF ONEENERGY IBIS SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 6.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN SOMERSET COUNTY, MARYLAND

9387    Date Filed:  July 10, 2015
IN THE MATTER OF THE APPLICATION OF ONEENERGY BLUE STAR SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 6.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN KENT COUNTY, MARYLAND

9383    Date Filed:  June 16, 2015
IN THE MATTER OF THE APPLICATION OF ONEENERGY SUNFISH SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 6.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN QUEEN ANNE'S COUNTY, MARYLAND

9380    Date Filed:  May 11, 2015
IN THE MATTER OF THE APPLICATION OF GREAT BAY SOLAR I, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 150.0 MW SOLAR PHOTOVOLTAIC GENERATIONG FACILITY IN SOMERSET COUNTY, MARYLAND

9375    Date Filed:  February 02, 2015
IN THE MATTER OF THE APPLICATION OF ONEENERGY WYE MILLS SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 10.0 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN QUEEN ANNE'S COUNTY, MARYLAND

9370    Date Filed:  November 03, 2014
IN THE MATTER OF THE APPLICATION OF ONEENERGY DORCHESTER, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 15.5 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN DORCHESTER COUNTY, MARYLAND

9367    Date Filed:  October 28, 2014
IN THE MATTER OF THE APPLICATION OF DELMARVA POWER & LIGHT COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO REBUILD AN EXISTING 138 KV OVERHEAD TRANSMISSION LINE ON EXISTING RIGHT-OF-WAY FROM THE CHURCH SUBSTATION IN QUEEN ANNE'S COUNTY TO THE STEELE SUBSTATION IN CAROLINE COUNTY

9366    Date Filed:  October 20, 2014
IN THE MATTER OF THE APPLICATION OF LS-EGRET, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 15.0 MW SOLAR POLYCRYSTALLINE PHOTOVOLTAIC GENERATING FACILITY IN WICOMICO COUNTY, MARYLAND

9365    Date Filed:  October 17, 2014
IN THE MATTER OF THE APPLICATION OF CONSTELLATION SOLAR MC, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 20MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN HARFORD COUNTY, MARYLAND

9348    Date Filed:  April 01, 2014
IN THE MATTER OF THE APPLICATION OF ONEENERGY CAMBRIDGE SOLAR, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 3.3 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN DORCHESTER COUNTY, MARYLAND

9351    Date Filed:  March 16, 2014
IN THE MATTER OF THE APPLICATION OF ROCKFISH SOLAR LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY T0 CONSTRUCT A 10 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN CHARLES COUNTY, MARYLAND

9341    Date Filed:  February 18, 2014
IN THE MATTER OF THE APPLICATION OF PANDA-BRANDYWINE, L.P. AND KMC THERMO, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AUTHORIZING THE MODIFICATION OF THE PANDA-BRANDYWINE POWER PLANT

9338    Date Filed:  January 14, 2014
IN THE MATTER OF THE APPLICATION OF H.A. WAGNER LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AUTHORIZING THE MODIFICATION OF THE HERBERT A. WAGNER GENERATING STATION

9330    Date Filed:  July 19, 2013
IN THE MATTER OF THE APPLICATION OF MATTAWOMAN ENERGY, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A NOMINALLY RATED 859 MW GENERATING FACILITY IN PRINCE GEORGE'S COUNTY, MARYLAND

9329    Date Filed:  June 24, 2013
IN THE MATTER OF THE APPLICATION OF POTOMAC ELECTRIC POWER COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO REBUILD AN EXISTING DOUBLE CIRCUIT 230KV OVERHEAD TOWER LINE ON EXISTING RIGHT-OF-WAY FROM THE BURTONSVILLE SUBSTATION TO THE TAKOMA SUBSTATION IN PRINCE GEORGE'S COUNTY, MARYLAND

9327    Date Filed:  May 20, 2013
IN THE MATTER OF THE APPLICATION OF OLD DOMINION ELECTRIC COOPERATIVE, INC. FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTURCT A NOMINALLY RATED 1,000 MW GENERATING FACILILTY IN CECIL COUNTY, MARYLAND

9323    Date Filed:  May 06, 2013
IN THE MATTER OF THE APPLICATION OF BALTIMORE GAS AND ELECTRIC COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE NORTHEAST TRANSMISSION SYSTEM IMPROVEMENT PROJECT

9321    Date Filed:  April 15, 2013
IN THE MATTER OF THE APPLICATION OF DELMARVA POWER & LIGHT COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO REBUILD AN EXISTING 138 KV OVERHEAD TRANSMISSION LINE ON EXISTING RIGHT-OF-WAY FROM THE MARYLAND/DELAWARE STATE LINE TO THE CECIL SUBSTATION IN CECIL COUNTY, MARYLAND

9320    Date Filed:  April 09, 2013
IN THE MATTER OF THE APPLICATION OF CONSTELLATION POWER SOURCE GENERATION, INC. FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AUTHORIZING THE MODIFICATION OF THE RIVERSIDE GENERATING STATION IN BALTIMORE COUNTY, MARYLAND

9318    Date Filed:  April 02, 2013
IN THE MATTER OF THE APPLICATION OF DOMINION COVE POINT, LNG, LP FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A GENERATING STATION WITH A NAME-PLATE CAPACITY OF 130 MW AT THE DOMINION COVE POINT LIQUEFIED NATURAL GAS TERMINAL IN CALVERT COUNTY, MARYLAND

9314    Date Filed:  January 23, 2013
IN THE MATTER OF THE APPLICATION OF CHURCH HILL SOLAR FARM, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 6MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN QUEEN ANNE’S COUNTY, MARYLAND

9312    Date Filed:  December 21, 2012
IN THE MATTER OF THE APPLICATION OF DELMARVA POWER AND LIGHT COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A NEW 138 KV OVERHEAD TRANSMISSION LINE ON EXISTING RIGHT-OF-WAY FROM CHURCH SUBSTATION TO WYE MILLS SUBSTATION IN QUEEN ANNE'S COUNTY, MARYLAND

9309    Date Filed:  November 15, 2012
IN THE MATTER OF THE APPLICATION OF THE POTOMAC EDISON COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO REBUILD THE MARYLAND SEGMENT OF THE MT. STORM-DOUBS 500 KV ELECTRIC TRANSMISSION LINE IN FREDERICK COUNTY, MARYLAND

9297    Date Filed:  July 03, 2012
IN THE MATTER OF THE APPLICATION OF KEYS ENERGY CENTER, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A NOMINAL 735 MW GENERATING FACILITY IN PRINCE GEORGE'S COUNTY, MARYLAND

9282    Date Filed:  September 28, 2011
IN THE MATTER OF THE APPLICATION OF BALTIMORE GAS AND ELECTRIC COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE NORTHWEST TO DEER PARK 115 KV TRANSMISSION LINE EXTENSION PROJECT

9280    Date Filed:  September 07, 2011
IN THE MATTER OF THE APPLICATION OF CPV MARYLAND, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AUTHORIZING THE MINOR MODIFICATION OF ITS ST. CHARLES PROJECT, IN CHARLES COUNTY, MARYLAND.

9274    Date Filed:  June 16, 2011
IN THE MATTER OF THE APPLICATION OF BALTIMORE GAS AND ELECTRIC COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE PERRYMAN TO HARFORD TRANSMISSION LINE RELOCATION PROJECT

9272    Date Filed:  May 26, 2011
IN THE MATTER OF THE APPLICATION OF MARYLAND SOLAR LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 20 MW SOLAR PHOTOVOLTAIC GENERATING FACILITY IN WASHINGTON COUNTY, MARYLAND

9268    Date Filed:  April 22, 2011
IN THE MATTER OF THE APPLICATION OF BIG SAVAGE, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 138 KV GENERATOR LEAD LINE IN ALLEGANY COUNTY, MARYLAND AND REQUEST FOR EXPEDITED REVIEW

9264    Date Filed:  March 23, 2011
IN THE MATTER OF THE APPLICATION OF DELMARVA POWER & LIGHT COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A NEW 138 KV OVERHEAD TRANSMISSION LINE IN WORCHESTER COUNTY, MARYLAND TO THE MARYLAND/DELAWARE STATE LINE

9251    Date Filed:  January 12, 2011
IN THE MATTER OF THE APPLICATION OF BALTIMORE GAS AND ELECTRIC COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE BAGLEY TO GRACETON 230-KV TRANSMISSION LINE REBUILD PROJECT IN HARFORD COUNTY, MARYLAND

9246    Date Filed:  November 10, 2010
IN THE MATTER OF THE APPLICATION OF BALTIMORE GAS AND ELECTRIC COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 230 KV TRANSMISSION LINE CIRCUIT BETWEEN THE CONASTONE AND GRACETON SUBSTATIONS IN HARFORD COUNTY, MARYLAND

9244    Date Filed:  November 08, 2010
IN THE MATTER OF THE APPLICATION OF BALTIMORE GAS AND ELECTRIC COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR ITS JOPPATOWNE SUPPLY PROJECT

9243    Date Filed:  September 29, 2010
IN THE MATTER OF THE APPLICATION OF BALTIMORE GAS AND ELECTRIC COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE BAGLEY 230 KV TRANSMISSION LINE BYPASS

9239    Date Filed:  August 12, 2010
IN THE MATTER OF THE APPLICATION OF THE POTOMAC EDISON COMPANY D/B/A ALLEGHENY POWER FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO MODIFY THE MONOCACY-RINGGOLD-CARROLL TRANSMSSION LINE IN FREDERICK, WASHINGTON AND CARROLL COUNTIES, MARYLAND

9229    Date Filed:  April 28, 2010
IN THE MATTER OF THE APPLICATION OF MIRANT MID-ATLANTIC, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AUTHORIZING THE MODIFICATION OF THE MORGANTOWN GENERATING STATION IN CHARLES COUNTY, MARYLAND

9227    Date Filed:  April 09, 2010
IN THE MATTER OF THE REQUEST OF CONSTELLATION POWER SOURCE GENERATION, INC. FOR A NEW AIR CONSTRUCTION AUTHORIZATION TO REPLACE THE EXPIRED AIR CONSTRUCTION AUTHORIZATION INCLUDED IN THE CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY GRANTED IN CASE NO. 9132.

9223    Date Filed:  March 10, 2010
IN THE MATTER OF THE APPLICATION OF THE POTOMAC EDISON COMPANY D/B/A ALLEGHENY POWER FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT THE MARYLAND SEGMENTS OF A 765 KV ELECTRIC TRANSMISSION LINE AND A SUBSTATION IN FREDERICK COUNTY, MARYLAND

9222    Date Filed:  March 04, 2010
IN THE MATTER OF THE PETITION OF BIG SAVAGE LLC FOR AN EXPEDITED DETERMINATION THAT IT IS ELIGIBLE TO OBTAIN A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT AN ASSOCIATED TRANSMISSION LINE THAT WILL INTERCONNECT AN OUT-OF-STATE WIND GENERATING FACILITY TO A MARYLAND SUBSTATION

9218    Date Filed:  January 26, 2010
IN THE MATTER OF THE APPLICATION OF CALVERT CLIFFS 3 NUCLEAR PROJECT, LLC AND UNISTAR NUCLEAR OPERATING SERVICES, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY AUTHORIZING THE MODIFICATION OF THE CALVERT CLIFFS UNIT 3 PROJECT AT CALVERT CLIFFS IN CALVERT COUNTY, MARYLAND

9199    Date Filed:  May 22, 2009
IN THE MATTER OF THE APPLICATION OF ENERGY ANSWERS INTERNATIONAL, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A 120 MW GENERATING FACILITY IN BALTIMORE, MARYLAND

9198    Date Filed:  May 19, 2009
IN THE MATTER OF THE APPLICATION OF THE POTOMAC EDISON COMPANY ON BEHALF OF PATH ALLEGHENY TRANSMISSION COMPANY, LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT THE MARYLAND SEGMENTS OF A 765 KV ELECTRIC TRANSMISSION LINE AND A SUBSTATION IN FREDERICK COUNTY, MARYLAND

9191    Date Filed:  May 06, 2009
IN THE MATTER OF THE APPLICATION OF SYNERGICS ROTH ROCK WIND ENERGY, LLC AND SYNERGICS WIND ENERGY, LLC FOR AN EXEMPTION OF THE CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY REQUIREMENT TO CONSTRUCT A 50-MW WIND GENERATION FACILITY LOCATED IN OAKLAND IN GARRETT COUNTY, MARYLAND.